Quick answer
Housing society redevelopment in Bandra follows the Maharashtra government's Section 79A guidelines: a general body resolution, a project management consultant, a transparent tender, and approval by at least 51% of members (most societies aim for consent from all members). Members typically get 25–45% more carpet area, rent during construction and a corpus, and the project takes 30–42 months.
On this page
- Key takeaways
- Why Bandra societies are redeveloping
- The 79A redevelopment process
- Builder model vs self-redevelopment
- Construction cost for redevelopment in Bandra
- How much FSI and TDR a Bandra plot can actually load
- A worked example: a 32-member Bandra society
- PMC selection, tender comparison and financing at Bandra's scale
- Disputes that surface in Bandra redevelopments
- Heritage grading and what it allows a Bandra bungalow cluster to rebuild
- Frequently asked questions
Key takeaways
- Appoint an independent PMC/architect before talking to any builder.
- Compare offers on carpet area, rent, corpus and bank guarantee — not just the headline area.
- Self-redevelopment keeps sale-flat profit with members.
- Approvals in Bandra go through the Brihanmumbai Municipal Corporation (BMC/MCGM).
01Why Bandra societies are redeveloping
Bandra is a premium, sea-facing suburb where heritage bungalows give way to redevelopment towers under CRZ review. Buildings from the 1960s–1990s are reaching the end of their design life, lack lifts and parking, and face rising repair bills. Higher FSI under DCPR 2034 and TDR availability make redevelopment financially attractive.
02The 79A redevelopment process
Follow the government guidelines to keep the process transparent and legally sound:
- Special general body meeting to start the process
- Appoint a project management consultant (PMC) and architect
- Structural audit and feasibility report
- Tender floated; offers from builders or contractors
- Comparison statement shared with all members
- SGM selects the developer with written consent
- Development agreement registered; bank guarantee obtained
- Permissions, shifting, construction and possession
03Builder model vs self-redevelopment
In the builder model, a developer funds the project and keeps the sale flats. In self-redevelopment, the society appoints a contractor, raises finance and sells the extra flats itself — usually leaving members 30–60% more area or a large corpus.
MumbaiConstructions works as the society's construction partner for self-redevelopment: BOQ-based contract, quality reports to the committee and staged payments linked to progress.
04Construction cost for redevelopment in Bandra
High-rise RCC construction typically runs ₹3,000–₹4,500 per sq.ft. depending on height, basement parking, podium and finishes. Premiums, TDR, GST and rent to members are separate and must be part of the feasibility.
05How much FSI and TDR a Bandra plot can actually load
Bandra's redevelopment stock splits into two very different vintages: standalone 1940s-60s bungalows on large individual plots in the Pali Hill and Chapel Road pockets, and 1970s-80s cooperative ground+4 walk-ups elsewhere in Bandra West and East. Under DCPR 2034, the base FSI plus fungible FSI plus purchasable TDR together set the redevelopment envelope, but the width of the road fronting the plot caps how much TDR can be loaded onto it. Many of Bandra's internal bungalow lanes are narrower than 9 metres, which keeps loadable FSI lower there than on arterial frontages like Linking Road or SV Road, even for plots of similar size.
A meaningful share of Bandra's bungalow clusters carry heritage-grade listing, which adds a facade and design-review step before any redevelopment proposal is sanctioned, separate from and in addition to the floor-space calculation. Coastal-facing plots west of Carter Road also sit inside CRZ review bands, where ground coverage and setback limits can bind before FSI even becomes the constraint — a society there should get a CRZ applicability check done before finalising a redevelopment brief, not after.
Construction cost in Bandra also runs at the upper end of the stated high-rise band — closer to ₹4,000-4,500/sq. ft than ₹3,000/sq. ft — once a society factors in higher finishing specification expectations, deeper foundations where soil conditions near the coast demand it, and the premium labour and material logistics of working on tight bungalow-lane sites. A tender quoting the lower end of the band for a coastal Bandra plot deserves a specific question about what finishing and foundation scope is actually included.
06A worked example: a 32-member Bandra society
Take a hypothetical 32-member society on a 2,200 sq. m plot (about 23,680 sq. ft), with members currently holding an average of 650 sq. ft carpet each — 20,800 sq. ft of existing carpet in total. On a mid-width Bandra road, combined base, fungible and TDR-loaded FSI commonly works out to roughly 2.6-2.8 times the plot area, putting total buildable potential around 63,000-66,000 sq. ft.
If each member is offered 35% more carpet area as rehab, that consumes about 28,080 sq. ft, leaving roughly 35,000 sq. ft of free-sale area for the developer to monetise. At the ₹3,000-4,500/sq. ft high-rise construction band applied across the full ~64,000 sq. ft built-up area, raw construction cost alone runs approximately ₹19-28 crore, before land premiums, consultant fees and the corpus commitment — numbers a managing committee should ask any bidder to show, not just quote a headline rate for.
Where the heritage grading applicable to a specific structure permits only facade retention rather than full redevelopment, the achievable buildable area in this example would be constrained behind the retained facade, typically reducing efficient floor-plate design and therefore trimming realistic free-sale area by a meaningful margin relative to the unconstrained estimate above — a reason heritage-grade confirmation should precede any area modelling, not follow it.
07PMC selection, tender comparison and financing at Bandra's scale
At Bandra's plot values, a project management consultant needs demonstrated experience with CRZ-NOC processing and heritage-precinct approvals, not just general redevelopment credentials — ask for at least two completed references in the same ward. Tender comparisons should separate the quoted construction rate per sq. ft from structural consultant fees, CRZ clearance timelines (which can add several months), and escalation clauses, since bidders sometimes quote a lean construction figure while loading costs elsewhere.
Self-redevelopment financing at this scale typically requires a larger construction-finance facility than in mid-tier suburbs, because high land value raises both the loan quantum and the lender's due-diligence bar. Lenders generally want to see the society's own corpus or reserve fund alongside a bank guarantee structure before releasing funds in tranches tied to construction milestones.
Bandra societies pursuing self-redevelopment should also budget for stamp duty and registration costs on the additional carpet area allotted to each member, since the incremental area received under a redevelopment scheme is typically subject to stamp duty at the time of the new allotment agreement — a cost many committees overlook until the conveyance stage, by which point it's too late to negotiate the developer absorbing it.
- Confirm CRZ/heritage NOC status before inviting tenders, not after
- Separate construction rate from consultant and clearance costs in every bid
- Check bidder's track record on at least two comparable Bandra-area projects
- Match loan disbursal tranches to verified construction milestones, not calendar dates
08Disputes that surface in Bandra redevelopments
Dissent is common where older owners hold legacy tenancy-linked arrangements, or where ground-floor units carry separate commercial rights negotiated decades ago — these members often want bespoke terms rather than the uniform offer given to residential members. A second recurring issue is title: a number of older Bandra buildings were constructed without a completion certificate, so OC-holder and non-OC-holder flats within the same society can face different documentation hurdles when the redeveloper structures the new allotment agreements.
Both issues are typically resolved before construction starts — title and OC gaps need regularisation as a condition precedent in the development agreement, and commercial-rights holders are usually given a separate annexure covering their unit rather than being folded into the standard member schedule. Where a developer exits mid-project, the bank guarantee the society holds is the first recourse, followed by a fresh tender to appoint a replacement developer against the part-built structure.
A further Bandra-specific dispute arises where heritage-grading restrictions reduce the achievable area after members have already been pitched a larger scheme — as with the AAI height-cap disputes in Santacruz and Borivali, this is best avoided by making any area or floor-count commitment in the development agreement explicitly conditional on the final heritage-cleared design envelope, not a fixed promise made before grading is confirmed.
09Heritage grading and what it allows a Bandra bungalow cluster to rebuild
Heritage-listed structures in Mumbai are typically graded by the level of intervention permitted, with the strictest grade preserving a building largely as-is and more lenient grades allowing fuller redevelopment behind a retained facade or in a manner sympathetic to the surrounding precinct's character — a Bandra bungalow cluster's grade determines whether redevelopment can proceed as a conventional tower or must accommodate facade retention and a design-review process specific to the precinct.
Because grading is assessed structure-by-structure rather than suburb-wide, two adjoining Bandra bungalows can carry different grades and therefore different redevelopment latitude — a society should get written grading confirmation for its specific structures before assuming a neighbouring, differently graded building's redevelopment scope applies equally to its own.
Get a free site visit in Bandra
MumbaiConstructions is a civil construction company and turnkey contractor serving Bandra and the wider Mumbai Metropolitan Region since 2009. Share your plot or building details and a project engineer will visit, check feasibility and send a line-item BOQ within 7 working days — no obligation.
Frequently asked questions
How much extra area do members get in Bandra?
Typically 25–45% extra carpet area in a builder deal, and often more in self-redevelopment, depending on plot size, road width and FSI.
Is 100% consent required for society redevelopment?
The government guidelines require a majority decision, but most societies aim for all members on board to avoid litigation.
Who pays rent during construction?
In a builder model the developer pays monthly rent and shifting charges. In self-redevelopment the society budgets it in the project finance.