Quick answer
Housing society redevelopment in Bhandup follows the Maharashtra government's Section 79A guidelines: a general body resolution, a project management consultant, a transparent tender, and approval by at least 51% of members (most societies aim for consent from all members). Members typically get 25–45% more carpet area, rent during construction and a corpus, and the project takes 30–42 months.
On this page
- Key takeaways
- Why Bhandup societies are redeveloping
- The 79A redevelopment process
- Builder model vs self-redevelopment
- Construction cost for redevelopment in Bhandup
- From industrial belt to township and mid-rise construction
- A worked example: a 36-member Bhandup society
- PMC selection and the township-amalgamation question
- Common disputes in Bhandup redevelopments
- Utility connection timelines in a still-developing infrastructure zone
- Frequently asked questions
Key takeaways
- Appoint an independent PMC/architect before talking to any builder.
- Compare offers on carpet area, rent, corpus and bank guarantee — not just the headline area.
- Self-redevelopment keeps sale-flat profit with members.
- Approvals in Bhandup go through the Brihanmumbai Municipal Corporation (BMC/MCGM).
01Why Bhandup societies are redeveloping
Bhandup is a former industrial belt now seeing township and mid-rise construction. Buildings from the 1960s–1990s are reaching the end of their design life, lack lifts and parking, and face rising repair bills. Higher FSI under DCPR 2034 and TDR availability make redevelopment financially attractive.
02The 79A redevelopment process
Follow the government guidelines to keep the process transparent and legally sound:
- Special general body meeting to start the process
- Appoint a project management consultant (PMC) and architect
- Structural audit and feasibility report
- Tender floated; offers from builders or contractors
- Comparison statement shared with all members
- SGM selects the developer with written consent
- Development agreement registered; bank guarantee obtained
- Permissions, shifting, construction and possession
03Builder model vs self-redevelopment
In the builder model, a developer funds the project and keeps the sale flats. In self-redevelopment, the society appoints a contractor, raises finance and sells the extra flats itself — usually leaving members 30–60% more area or a large corpus.
MumbaiConstructions works as the society's construction partner for self-redevelopment: BOQ-based contract, quality reports to the committee and staged payments linked to progress.
04Construction cost for redevelopment in Bhandup
High-rise RCC construction typically runs ₹3,000–₹4,500 per sq.ft. depending on height, basement parking, podium and finishes. Premiums, TDR, GST and rent to members are separate and must be part of the feasibility.
05From industrial belt to township and mid-rise construction
Bhandup's redevelopment pipeline increasingly involves plots that sit near former industrial land now being repurposed for larger township-scale residential development, alongside its older stock of 1970s-80s cooperative ground+4 buildings. Under DCPR 2034, standalone cooperative society plots here follow the standard FSI/fungible/TDR framework with road-width-capped loading, while societies near larger township parcels sometimes get approached about amalgamation into the township's master layout, similar to the dynamic seen in Goregaon.
Because Bhandup's industrial-to-residential conversion is relatively recent compared to more established suburbs, infrastructure capacity (water, drainage, road access) around some redevelopment plots is still catching up to the pace of new construction, which societies should factor into their expectations around utility connection timelines during the approval process.
Bhandup's transition from industrial to residential land use also means some redevelopment plots carry environmental due-diligence considerations around prior industrial use — a soil or land-use history check is a reasonable precaution before finalising a redevelopment brief on any plot with a documented industrial past, even where current zoning is purely residential.
06A worked example: a 36-member Bhandup society
A 36-member society on a 1,800 sq. m plot (about 19,375 sq. ft), members averaging 460 sq. ft carpet, starts at 16,560 sq. ft existing carpet. Typical DCPR 2034 loading for a standard Bhandup residential road gives buildable potential of roughly 2.3 times plot area, about 44,560 sq. ft.
Rehab at 30% extra carpet needs about 21,530 sq. ft, leaving roughly 23,030 sq. ft for free sale. Construction on the ~45,000 sq. ft total at the high-rise band is estimated at ₹13-20 crore, a range committees can use to check that a bidder's rehab and corpus offer is realistically funded.
If water or drainage connection approval for the new building takes longer than the standard sanction process given the area's still-developing infrastructure, the gap between structural completion and final occupancy certificate can widen by a few months beyond what the construction schedule alone would suggest — a timeline risk distinct from the FSI and construction-cost arithmetic itself, and one a committee should flag with its PMC early.
07PMC selection and the township-amalgamation question
Where a society is approached about joining a neighbouring township's master layout, the same evaluation discipline applies as in Goregaon: get the independent-tender option costed alongside the township offer before the general body votes, rather than defaulting to the larger developer's proposal on reputation alone.
For standalone schemes, self-redevelopment financing follows the general MMR pattern of milestone-linked disbursal against a bank guarantee, though committees should confirm with their PMC that utility connection approvals (water and drainage capacity specifically) won't become an unplanned bottleneck given the area's still-developing infrastructure.
Given Bhandup's infrastructure capacity is still catching up in places, committees should ask their PMC to confirm utility approval status as an explicit go/no-go milestone in the tender process, rather than assuming any bidder's general assurance that connections will be available when needed.
08Common disputes in Bhandup redevelopments
Beyond the standard dissenting-member and title-gap issues seen across the eastern suburbs, a Bhandup-specific friction point is disagreement over accepting a township-amalgamation offer versus an independent redevelopment, resolved the same way as in Goregaon — by costing both paths before the vote.
Where a developer exits mid-project, bank guarantee enforcement followed by re-tender against the part-built structure is the standard recourse; committees should also confirm during re-tender that any utility or infrastructure approvals already secured transfer to the replacement developer rather than needing to be reapplied for.
A further Bhandup-specific dispute arises when members expect a township-style amenity standard, given nearby large developments, but the independent redevelopment path can't support that specification at the project's actual scale — managing this expectation gap early, by showing members a realistic amenity budget tied to the project's own free-sale economics, avoids later disappointment and renegotiation demands.
09Utility connection timelines in a still-developing infrastructure zone
Because a meaningful share of Bhandup's redevelopment activity sits near land only recently converted from industrial to residential use, water supply and drainage capacity in some pockets is still catching up to the pace of new construction — societies should confirm with the municipal utility department, not just the developer, what connection capacity is actually available before assuming a standard timeline.
Where capacity is constrained, developers sometimes need to fund an upgrade to the local utility network as a condition of final occupancy certification — a cost that should be clarified upfront as either the developer's responsibility or a shared cost, rather than surfacing as a dispute once the building is structurally complete but can't be occupied.
Get a free site visit in Bhandup
MumbaiConstructions is a civil construction company and turnkey contractor serving Bhandup and the wider Mumbai Metropolitan Region since 2009. Share your plot or building details and a project engineer will visit, check feasibility and send a line-item BOQ within 7 working days — no obligation.
Frequently asked questions
How much extra area do members get in Bhandup?
Typically 25–45% extra carpet area in a builder deal, and often more in self-redevelopment, depending on plot size, road width and FSI.
Is 100% consent required for society redevelopment?
The government guidelines require a majority decision, but most societies aim for all members on board to avoid litigation.
Who pays rent during construction?
In a builder model the developer pays monthly rent and shifting charges. In self-redevelopment the society budgets it in the project finance.