Society Redevelopment in Chembur: Process, Costs & Self-Redevelopment Option

By MumbaiConstructions engineering team · Updated 2026-10-01 · 7 min read

Quick answer

Housing society redevelopment in Chembur follows the Maharashtra government's Section 79A guidelines: a general body resolution, a project management consultant, a transparent tender, and approval by at least 51% of members (most societies aim for consent from all members). Members typically get 25–45% more carpet area, rent during construction and a corpus, and the project takes 30–42 months.

Key takeaways

  • Appoint an independent PMC/architect before talking to any builder.
  • Compare offers on carpet area, rent, corpus and bank guarantee — not just the headline area.
  • Self-redevelopment keeps sale-flat profit with members.
  • Approvals in Chembur go through the Brihanmumbai Municipal Corporation (BMC/MCGM).

01Why Chembur societies are redeveloping

Chembur is a former refinery-belt suburb now dense with high-rise redevelopment. Buildings from the 1960s–1990s are reaching the end of their design life, lack lifts and parking, and face rising repair bills. Higher FSI under DCPR 2034 and TDR availability make redevelopment financially attractive.

02The 79A redevelopment process

Follow the government guidelines to keep the process transparent and legally sound:

  • Special general body meeting to start the process
  • Appoint a project management consultant (PMC) and architect
  • Structural audit and feasibility report
  • Tender floated; offers from builders or contractors
  • Comparison statement shared with all members
  • SGM selects the developer with written consent
  • Development agreement registered; bank guarantee obtained
  • Permissions, shifting, construction and possession

03Builder model vs self-redevelopment

In the builder model, a developer funds the project and keeps the sale flats. In self-redevelopment, the society appoints a contractor, raises finance and sells the extra flats itself — usually leaving members 30–60% more area or a large corpus.

MumbaiConstructions works as the society's construction partner for self-redevelopment: BOQ-based contract, quality reports to the committee and staged payments linked to progress.

04Construction cost for redevelopment in Chembur

High-rise RCC construction typically runs ₹3,000–₹4,500 per sq.ft. depending on height, basement parking, podium and finishes. Premiums, TDR, GST and rent to members are separate and must be part of the feasibility.

05From refinery belt to dense high-rise redevelopment

Chembur's older residential stock grew up alongside its refinery and industrial belt, and much of it is now 1960s-80s ground+2/3 construction well past its structural design life, which is part of why Chembur has one of the denser concentrations of active high-rise redevelopment in the eastern suburbs. Under DCPR 2034, plots near the refinery buffer zone can face additional safety-distance considerations during sanction, distinct from the standard FSI and height process, though this affects a defined subset of Chembur's residential stock rather than the whole suburb.

Chembur's station-adjacent and arterial-road plots (such as those along the Eastern Express Highway service roads) see considerably heavier TDR loading potential than its older interior residential lanes, following the same road-width-capping logic seen across DCPR 2034 jurisdiction, so plot location within the suburb matters as much as plot size for a society estimating its redevelopment potential.

Chembur's redevelopment pipeline has also benefited from the broader decline of heavy industrial activity in the immediate area over recent decades, which has gradually reduced the practical footprint of any safety-distance buffer affecting nearby plots — though this is a gradual regulatory and operational process, and a society should still confirm current buffer status rather than assuming historical industrial decline has automatically lifted any restriction.

06A worked example: a 50-member Chembur society

A 50-member society on a 2,400 sq. m plot (about 25,830 sq. ft) on a moderately wide road away from any refinery-buffer zone, members averaging 480 sq. ft carpet, starts at 24,000 sq. ft existing carpet. Typical DCPR 2034 loading gives buildable potential of roughly 2.5 times plot area, about 64,580 sq. ft.

Rehab at 32% extra carpet needs about 31,680 sq. ft, leaving close to 32,900 sq. ft for free sale. Construction on the ~65,000 sq. ft total at the high-rise band is estimated at ₹19-29 crore, a healthy enough free-sale margin that committees should expect competitive bidder interest for a plot of this profile.

If the plot instead sits within the refinery safety-distance buffer, sanctioned footprint or height can be reduced relative to this example, trimming free-sale area in a manner similar to the AAI height-cap effect seen in Santacruz — committees uncertain whether their plot falls inside this buffer should get it confirmed by the relevant authority before assuming the unrestricted-plot numbers above apply to them.

07PMC selection and financing in a refinery-adjacent context

For any Chembur plot near the refinery buffer, the PMC should confirm safety-distance applicability early, since this can affect the sanctioned footprint independent of FSI — a bidder unfamiliar with this check may underquote the approval timeline. For plots away from the buffer zone, standard PMC and tender-comparison discipline (separating construction rate from consultant and clearance costs, requiring floor-wise cost breakdowns on larger projects) applies as elsewhere in the eastern suburbs.

Self-redevelopment financing follows the general MMR pattern, with refinery-buffer-adjacent projects needing a longer pre-construction approval window built into the loan schedule, similar in principle to the CRZ and green-buffer timelines seen in Malad and Borivali.

Chembur's mix of refinery-buffer-affected and unaffected plots means, as in Borivali, that a PMC's cost and timeline benchmark should come from a comparable-constraint project rather than a generic suburb-wide average.

08Common disputes in Chembur redevelopments

Standard pitfalls apply: dissenting members, OC-holder versus non-OC-holder title gaps (common in Chembur's older, pre-OC-era buildings), and bank guarantee enforcement followed by re-tender if a developer exits mid-project — all resolved through the same documented-consent, pre-construction-regularisation, and guarantee-enforcement mechanisms used across the eastern suburbs.

A Chembur-specific friction point arises when a refinery-buffer safety check reduces the sanctioned footprint after members have already been pitched a larger area — as with the height-cap disputes in Santacruz and Borivali, this is best avoided by making any area commitment in the development agreement explicitly conditional on final sanctioned footprint.

09Refinery safety-distance considerations for Chembur plots

Residential plots near Chembur's refinery and industrial installations can fall within a defined safety-distance buffer that limits construction density or height as a precaution, independent of the standard DCPR 2034 FSI and height sanction process — this applies to a specific subset of Chembur's stock rather than the suburb broadly, so proximity alone isn't a reliable guide to whether a plot is affected.

A society uncertain whether its plot falls within this buffer should raise the question with its architect and the relevant authority at the earliest planning stage, since a safety-distance restriction discovered only after a development agreement is signed can force a costly redesign of an already-tendered scheme.

Get a free site visit in Chembur

MumbaiConstructions is a civil construction company and turnkey contractor serving Chembur and the wider Mumbai Metropolitan Region since 2009. Share your plot or building details and a project engineer will visit, check feasibility and send a line-item BOQ within 7 working days — no obligation.

Frequently asked questions

How much extra area do members get in Chembur?

Typically 25–45% extra carpet area in a builder deal, and often more in self-redevelopment, depending on plot size, road width and FSI.

Is 100% consent required for society redevelopment?

The government guidelines require a majority decision, but most societies aim for all members on board to avoid litigation.

Who pays rent during construction?

In a builder model the developer pays monthly rent and shifting charges. In self-redevelopment the society budgets it in the project finance.

ISO 9001:2015 aligned QA processGST & PAN registered contractorLabour insurance & site safety planRERA-compliant documentation supportDefect liability period on every handover

Planning a project in Chembur?

Free site visit, feasibility check and a line-item BOQ within 7 working days.

Powered by IRPR